10T heat treatment furnace production line

Description:一.Project summary1.1 Production capacity and product plan1.1.1 Name and quantity:Materials automated heat treatment production line equipment will be installed in the heat treatment workshop, 1 set heat treatment furnace , automatic loading and unl..

Description

一.Project summary

1.1 Production capacity and product plan
1.1.1 Name and quantity:
Materials automated heat treatment production line equipment will be installed in the heat treatment workshop, 1 set heat treatment furnace , automatic loading and unloading material 1 set, the loading station 2 sets, a pool 1 set (including circulation and cooling pool selected), design of control system and the cable service life > 10 years.
1.1.2 Satisfying technology and Process requirement for heat treatment furnace
⑴ The form of the production line furnace:After the heat treatment of the workpiece is completed, the forklift quickly enters the furnace and sets the workpiece out of the furnace, and quickly falls into the sink, and the whole process is completed within 35 seconds.
High production efficiency and flexible operation ensure the quality and maneuverability of the workpiece.
⑵ Production line composition: 
Number Items Quantity
1 Heat treatment furnace(1 hardening1 tempering) 2 sets
2 10tOrbital heat treatment robot (loading machine) 1 set
3 Quenching tank (user-provided) 1 set
4 Loading tray (user-provided) 3 sets
5 Cistern cycle mechanism 1 set
6 Cistern cooling mechanism (optional or user-provided) 1 set
7 Loading station 2 sets
⑶ Heating method: liquefied petroleum gas(LPG);
⑷ The way of the loading for the workpiece:Adopt heat treatment robot;
⑸ Use: Mainly used for automatic heat treatment of materials. 

二.Equipment model, specification and main technical scheme
Project Description: In order to meet the requirements of automatic heat treatment of materials, two sets of heat treatment equipment robots need to be built into a production line for heat treatment furnace. At present, The production line is the most advanced technology in China.
The production line has a high degree of logistics automation. Automatic completion of loading, unloading, in to the furnace, out of the furnace, quenching and other processes, not only improve the working environment, but also effectively guarantee the quality of the heat treatment equipment without the man-made influence. For large parts can be realized without tooling loading and unloading directly, significantly reducing the consumption of energy and tooling.
Fast transfer of heating furnace to quenching tank can be realized. The quenching time can be less than 35 seconds.

Supply Ability

  • 60 Set/Sets per Year

Packing & Delivery

  • The furnace is nude packed but duly fixed inside the container.
  • The nearest sea port is Shanghai port which is the largest and most convenient port over China.
  • The delivery time is 45-120 days after receipt of down payment.
  • The furnace is usually loaded into normal containers (20GP or 40GP) or flat racks.
  • Usually machine is packed with wooden case and standard export carton, plywood carton or as your requirement.

Our Services

  • Reply your inquiry within 48 working hours
  • Experienced engineer instruct and sales communicate with you in fluent English.
  • Exclusive and unique solution can be provided to our customer by our well-trained and professional engineers and staff.
  • More contact with users, communicate with each other, to ensure that the manufacturing products meet the needs of customers.
  • Production: strict quality standard, to produce machine and induction coils.
  • Installation on site and commissioning in the condition of cold and hot, to ensure the normal use.
  • Tracking goods shipping and provide bill of lading,invoice,packing list and other documents what you need.
  • Provide install and technology instruction by sending drawings, email, or telephone,video.
  • If you need, will arrange one engineer to your place,instruct install machine and training operators.
  • Responsible for free training of technology, service and operation personnel's theory, maintenance and operation skills, to make users use production right and expertly. Training is in the section of device debugging and test run.
  • After equipment final acceptance, quality guarantee period is for 12 months, the supplier replace and repair for free when the damage is caused by production and materials during the warranty period. To the damage out of warranty period, the supplier should give preferential service and the supply of parts (only accept costs), and provide lifelong offer after-sale service.
10T heat treatment furnace production line

Supply Ability

  • 60 Set/Sets per Year

Packing & Delivery

  • The furnace is nude packed but duly fixed inside the container.
  • The nearest sea port is Shanghai port which is the largest and most convenient port over China.
  • The delivery time is 45-120 days after receipt of down payment.
  • The furnace is usually loaded into normal containers (20GP or 40GP) or flat racks.
  • Usually machine is packed with wooden case and standard export carton, plywood carton or as your requirement.

Our Services

  • Reply your inquiry within 48 working hours
  • Experienced engineer instruct and sales communicate with you in fluent English.
  • Exclusive and unique solution can be provided to our customer by our well-trained and professional engineers and staff.
  • More contact with users, communicate with each other, to ensure that the manufacturing products meet the needs of customers.
  • Production: strict quality standard, to produce machine and induction coils.
  • Installation on site and commissioning in the condition of cold and hot, to ensure the normal use.
  • Tracking goods shipping and provide bill of lading,invoice,packing list and other documents what you need.
  • Provide install and technology instruction by sending drawings, email, or telephone,video.
  • If you need, will arrange one engineer to your place,instruct install machine and training operators.
  • Responsible for free training of technology, service and operation personnel's theory, maintenance and operation skills, to make users use production right and expertly. Training is in the section of device debugging and test run.
  • After equipment final acceptance, quality guarantee period is for 12 months, the supplier replace and repair for free when the damage is caused by production and materials during the warranty period. To the damage out of warranty period, the supplier should give preferential service and the supply of parts (only accept costs), and provide lifelong offer after-sale service.